Parish Council Agree to Fund Play Area at the West Way Sports Hub Development

10th of May, 2021

Works at West Way Sports Hub were progressing in accordance with the programme.  Completion and opening of the changing pavilion, artificial grass pitch and compact athletics track was expected week commencing 12 July 2021.

The Parish Council have previously agreed to increase the budget for play equipment from £20,000 to £30,000 and provide a further £5,000 to extend the proposed footpaths.

Councillors Keith Ashton and Matt Lynch will be representing the Parish Council on the Tendering Evaluation Panel. A date for the evaluation panel to progress the tender package for the play area are still to be confirmed.